Esther Perez Carvajal Elementary School

Bond 2020
Program Phase 3 School
Status: Design Development

Planned Scope of Work* 

  • New interior and exterior security cameras
  • New security vestibule
  • Overhaul historic original buildings
  • Overhaul or replace all classrooms and science labs
  • Overhaul or replace special education classrooms
  • Overhaul or replace main office and main entrance to include secured vestibule
  • Renovate gym and physical education support spaces
  • Overhaul or replace student dining and kitchen
  • Replace old exterior windows with new energy-efficient windows
  • Update mechanical systems to the latest energy efficiency and indoor air quality standards
  • Add new outdoor learning opportunities, or replace existing ones
  • Re-pave and re-surface parking lots and driveways
  • Add, replace, and/or repair existing playground equipment
 

Project Information

The district provided an update on the Carvajal Elementary project during a community meeting on Jan. 16, 2025, at Rhodes Middle School. The meeting also included updates for Rhodes, Tafolla Middle School, Lanier High School, and Irving Dual Language Academy. View the meeting presentation (link below) for the latest on the project and check back for updates.

Meeting presentation

Updated 1/17/25

Questions & Answers:
Bond 2020 Renovations at Carvajal ES


What is the status of renovations at Carvajal Elementary?
Carvajal Elementary renovations are currently in design. To help address industry pressures during the pandemic, the bond projects were placed in phases to stagger construction.  The Carvajal renovation project, which was placed in Phase 3, came in over budget, based on initial designs. The district is working with the architect to bring the project within budget. 

What is included in the renovation?
The planned renovation includes a substantial overhaul of the campus, including classrooms; science labs; P.E. support spaces; cafeteria and kitchen; main office and main entrance; mechanical systems; window replacement; parking lots and driveways; and playground.

Additionally, the campus will receive security and technology upgrades, along with all SAISD schools.   

When will construction begin on our school?
The district must first complete the design phase, which is expected to last through summer 2026, with construction beginning fall 2026.

Will students need to be relocated to another campus during construction?
Decisions about project phasing and accommodations will be made when the project enters the construction phase. The district will communicate logistics with campus leadership to share with families.

When will we be able to use the newly renovated spaces?
Once the project is completed, a move-in date that coincides with a school break would need to be selected for move-in to the new spaces.

How will parents and students have a voice in the process?
Your principal will be forming a Project Advisory Team that includes parents, students, teachers, and community members to represent the larger Carvajal Elementary community. The group will provide input on the project during the design phase.

How can I stay informed about the progress of the project?
In addition to future community meetings and periodic updates from your campus, you can follow progress:  

  - On the bond website. You can also use the Bond 2020 button at the bottom left of the Carvajal Elementary homepage to link directly to your school’s project page. 
  - On Facebook, Instagram, and LinkedIn by following San Antonio ISD

 
Press ENTER key to focus on the active panel
your bond dollars at work
Photo Gallery
  • Bond 2020 community update meeting | January 2025

Renderings are conceptual and may differ from final design. 
Carvajal ES logo

Project Team
General Contractor:  
Flintco, LLC

Architect:  
DLR Group

SAISD Project Manager:  
Construction & Development Services Dept.

Trustee District #5:  
Stephanie Torres

Total Allocated Budget**
$31,583,550

**The total allocated budget, which includes architectural, engineering, and construction costs, may differ from the original budget due to program modifications necessitated by the rising cost of construction, the implementation of strategic district initiatives, or other program impacts