Project Completed!
********************************************************************************************
Latest Updates
Fall 2020:
98 percent of the 2016 bond scope is substantially complete turned over to faculty and staff on August 17, 2020, including modern classroom upgrades, front entry modifications, front exterior makeover with the addition of windows to classrooms, kitchen remodel and more.
May 2020: Construction is now in Phase 3 and Phase 4. These areas and site are in progress.
Auditorium and Back of House Area: In wall inspections ongoing currently, with ceiling framing over seating to start early to mid May. Painting also set to begin.
Kitchen: Completing resinous epoxy flooring, hoods and walk in coolers installation early to mid May. Completing ceramic wall tile.
Science Wing: Mechanical, electrical and plumbing work is ongoing in classrooms.
Site: Kitchen ramp ongoing, courtyard concrete ramps poured. Front entry ramp/sidewalk demolition started early to mid May.
4.23.19: Stakeholder Meeting. Click here for the presentation.
9.29.18: A Community Meeting took place in the Auditorium @ Sam Houston High School. Click here for the presentation.
A Project Advisory Team Meeting has not been held as of yet. A date will be determined for school leaders, faculty and members of the community to meet and discuss specific ideas for the project.