Project Completed!
********************************************************************************************
Latest Updates
Overall project completion currently scheduled for December 2020
Fall 2020:
Brand new upgraded and expanded classrooms greeted faculty and staff for the start of the 2020/21 school year. As students began arriving back on campus, they had the opportunity to eat in the new student dining space. It comes complete with a new kitchen for Child Nutrition Services.
The first four phases are now substantially complete. Mechanical and electrical upgrades in the library are also complete, including the wings housing P-Tech.
May 2020: Library – Painting in progress, along with final cleaning and addressing punch list items to mark ending of the phases.
Work to the front classroom wing continued with overhead electrical work, while wall line connections are prepared. Workers are framing areas of the wall that have been expanded to include sheetrock coverup, duct and piping installation.
Front Entry, or Area B of the project, maintains a concrete slab that is currently in progress as of Spring 2020.
Dining Area, or Area D of the project, includes ductwork in progress, ceiling cover up pending overhead inspection.
In the auditorium, the ceiling grid in the back of the house is in progress as of Spring 2020.
Around the Site: Temporary irrigation at softball field is complete, and excavation for new landscaping in front of school is in progress.
April 22, 2019: Stakeholder Meeting. Click here for the presentation.
September 29, 2018: A Community Meeting took place in the Cafeteria. Click here for the presentation.
March 21, 2018: A Project Advisory Team Meeting was held.